Helpful? 0

Capillary break over footing

We are unfortunately under some time constraints and are looking into damp proofing our foundation footing before the foundation wall is poured. How long should we wait before applying a damp proofing product? The product should also be able to dry quickly and at temperatures around 46 degrees Fahrenheit.
I should mention that the site is dry as a bone sand. Maybe we can go without a capillary break between the footing and foundation wall?

Asked by jessie pratt
Posted Tue, 11/20/2012 - 14:10

Tags:

2 Answers

Select your preferred way to display the comments and click "Save settings" to activate your changes.
1.
Helpful? 0

Jessie,
There is a discussion of various options here: What is a capillary break between the footing and foundation wall?

According to Robert Riversong, "UGL Drylock Latex Masonry Waterproofing dries in less than an hour, can be second coated in three hours and is ready for foundation in 24 hours."

Answered by Martin Holladay, GBA Advisor
Posted Tue, 11/20/2012 - 14:24

2.
Helpful? 0

Yes I have read them all, but unfortunately I can't find that product here.

Answered by jessie pratt
Posted Tue, 11/20/2012 - 14:30

Other Questions in General questions

Super insulating and soundproofing

In Green building techniques | Asked by Ryan Griffin | Nov 22, 14

Detail for stone veneer

In Green building techniques | Asked by Robert Holland | Nov 16, 14

Mid Roof Edge Vents / Ice Dams

In Energy efficiency and durability | Asked by Robert Eaton | Nov 23, 14

Blower door testing by floor or room?

In PassivHaus | Asked by Ryan Griffin | Nov 21, 14

Help with Green Addition and hyrdonic heat demo

In Green building techniques | Asked by Michael McArdle | Nov 23, 14
Register for a free account and join the conversation


Get a free account and join the conversation!
Become a GBA PRO!